PROJECT NAME
Baku-Tbilisi-Ceyhan Oil Pipeline & South Caucasus Gas Export Pipeline
LOCATION
Azerbaijan
CLIENT
Baku - Tbilisi - Ceyhan Pipeline Co. Ltd. (BTC) & South Caucasus Pipeline Co. (SCP)
SCOPE
Engineering, Procurement, Construction & Commissioning
DURATION
BTC 37 Months, SCP 19 Months
DATE OF COMPLETION
March 2006
Construction and Commissioning of 886 km crude oil and gas pipeline.
The principal components of the Pipeline System are:
- 443 km 42” diameter high pressure pipeline API 5L Gr X-70 SAW . from Sangachal Terminal to a tie-in point with the Georgian section of the pipeline near the Azerbaijan – Georgia border.
- 443 km 42” diameter high pressure pipeline API 5L Gr X-70 SAW laid in parallel to the Baku – Tbilisi – Ceyhan (BTC) Oil Pipeline;
- 24 nos. powered block valve stations
- 3 nos. check valve stations;